PV - Planned Value
Synonym: Budgeted Cost of Work Scheduled (BCWS) |
The authorized budget assigned to scheduled work.
|
|
EV - Earned Value
Synonym: Budgeted Cost of Work Performed (BCWP) |
The measure of work performed expressed in terms of the budget authorized for that work.
|
|
AC - Actual Costs
Synonym: Actual Cost of Work Performed (ACWP) |
The realized cost incurred for the work performed on an activity during a specific time period.
|
|
BAC - Budget at Completion
|
The sum of all budgets established for the work to be performed.
|
|
CV - Cost Variance
|
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
|
|
SV - Schedule Variance
|
The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value.
|
|
VAC - Variance at Completion
|
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
|
|
CPI - Cost Performance Index
|
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
|
|
SPI - Schedule Performance Index
|
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
|
|
EAC - Estimate at Completion
|
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
|
|
ETC - Estimate to Complete
|
The expected cost to finish all the remaining project work.
|
|
TCPI - To Complete Performance Index
|
The measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the budget available.
|
|
CPI - Cost Performance Index
|
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual costs.
EV / AC |
|
SPI - Schedule Performance Index
|
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
EV / PV |
|
EAC = BAC / CPI
|
What equation calculates the EAC if the CPI is expected to be the same for the remainder of the project?
|
|
EAC = AC + BAC - EV
|
What equation calculates the EAC if future work will be accomplished at the planned rate?
|
|
EAC = AC + Bottom-up ETC
|
What equation calculates the EAC if the initial plan is no longer valid?
|
|
EAC = AC + [ (BAC -EV) / (CPI X SPI) ]
|
What equation calculates the EAC if both the CPI and SPI influence the remaining work?
|
|
EV = Earned Value
|
What equation calculates the planned value of all the work completed to a point in time without reference to actual costs.
|
|
ETC = EAC - AC
|
What equation calculates the cost of completing the remaining authorized work, assuming work is proceeding on plan?
|
|
ETC = Reestimate
|
What equation calculates the cost of reestimating work from the bottom up?
|
|
TCPI = (BAC - EV) / (BAC - AC)
|
What equation calculates the efficiency that must be maintained in order to complete on plan?
|
|
TCPI = (BAC - EV) / (EAC - AC)
|
What equation calculates the efficiency that must be maintained in order to complete the current EAC?
|
|
CV = EV - AC
|
What equation calculates the difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time?
|
|
SV = EV - PV
|
What equation calculates the difference between the work completed to a point in time, usually the data date, and the work planned to be completed to the same point in time?
|
|
VAC = BAC - EAC
|
What equation calculates the estimated difference in cost at the completion of the project?
|
|
CPI = EV / AC
|
What equation calculates the CPI?
|
|
SPI = EV / PV
|
What equation calculates the SPI?
|
|
Positive = Under planned costs
Neutral = On planned cost Negative = Over planned cost |
Interpret: CV = EV - AC
|
|
Positive = Ahead of schedule
Neutral = On schedule Negative = Behind schedule |
Interpret: SV = EV - PV
|
|
Positive = Under planned costs
Neutral = On planned cost Negative = Over planned cost |
Interpret: VAC = BAC - EAC
|
|
Greater than 1.0 = Under planned cost
Exactly 1.0 = On planned cost (exactly on budget) Less than 1.0 = Over planned cost |
Interpret: CPI = EV / AC
|
|
Greater than 1.0 = Ahead of schedule
Exactly 1.0 = On schedule Less than 1.0 = Behind schedule |
Interpret: SPI = EV / PV
|
|
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete Less than 1.0 = Easier to complete |
Interpret: TCPI = (BAC - EV) / (BAC - AC)
|
|
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete Less than 1.0 = Easier to complete |
Interpret: TCPI = (BAC - EV) / (EAC - AC)
|
|
Performance Measurement Baseline
|
What is another term for the total of the planned value?
|