Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
29 Cards in this Set
- Front
- Back
Rics says what about risk management? |
Widely recognised as being concerned with both threat and opportunity |
|
What does rics management of risk 2015 link directly to? |
To Icms ipms and underpins them, will be mandatory soon |
|
Rics definition of risk |
An uncertain event or circumstance, that, if it occurs, will affect the outcome of a project/programme |
|
Latham said? |
No construction project is risk free. Risk can be managed, minimised, shared, transferred or accepted, it cannot be ignored |
|
Risk should be considered at |
All stages |
|
How do you identify risks? |
Facilitated workshops Self assessment Checklists Organisation charts Flow charts Prompt lists |
|
Risk analysis in bs 31010 |
Control analysis Likelihood and consequence |
|
Risk assessment is? |
The overall process of risk identification, risk analysis and risk evaluation |
|
After risk assessment comes? |
Risk treatment leaving residual risk after being treated |
|
Monitoring and tdviewing |
Risks and controls should be monitored and reviewed |
|
Risk register acts as |
A control document and assists as a means of monitoring the management of risks through a project |
|
Types of risk assessment |
Qualitative and quantitative |
|
Qualitative risk assessment |
Checklists Risk mapping |
|
Quantitative assessment |
Decision trees Sensitivity analysis Expected monetary value Monte Carlo simulations |
|
Wembley stadium |
Max price contract d&b 326 million Low bid 150 million loss. Failure to transfer risk cost them 430 million. Stadium complete 18 months late. No flexibility for problem solving in contract |
|
Heathrow term 5 |
4.3 billion Built on time and budget Highly innovative contracting system Cm consultancy employed. Baa accepted all construction risks confront and manage risks early. Terminal roof identified as a major risk (2.4 million) prototype paid for, cost and time savings achieved however 34 flights cancelled as staff not fsmiliar |
|
Hinckley point will be nearly 10% more than expected cost to rise 1.5bn to 19.6bn. Could be delayed by up to 15 months resulting in extra 700m costs |
Cross rail overruns of over a billion mainly due to design changes and low initial bids |
|
Nrm1 risks |
Design development risks Construction risks Employer change risks Employer other risks |
|
Nrm1 defines risk as |
The likelihood of an event or failure occurring and it’s consequences or impact |
|
Risk analysis also brings benefit to? |
Contractors |
|
Procurement |
Risk management and form of procurement are interlinked, optimum balance of risk, benefit and funding |
|
Risk response strategies |
Share - both have risk materials Transfer - best value for money Avoid - unacceptable level Retain - residual risk Reduce - value engineer |
|
Controllable and uncontrollable risks |
Controllable is curtain walking system Uncontrollable can’t be controlled or influenced by participants ie legislation |
|
Risk impact assessment |
Likelihood and impact |
|
Likelihood and impact equals |
Risk severity |
|
Methods of assessing risk under nrm1 |
Simple method of assessment Probabilistic analysis Sensitivity analysis |
|
Risk cost calculated by |
Percentage of base cost estimate. Sum of all four equals total risk allowance |
|
Risk allowances must only be |
Expended when the identified risks to which they relate occur |
|
Inflation is another rusk |
Tenet inflation construction inflation |