3 Cards in this Set
- Front
- Back
- 3rd side (hint)
Being assigned as a project manager, you noticed during project execution that conflicts arise in the team on both technical and interpersonal levels. What is an appropriate way of handling conflicts?1 |
Conflicts should be addressed early and usually in private, using a direct, collaborative approach. |
Executing Reference: PMBOK® Guide 5th Edition, page 518. |
|
What is the purpose of a project charter? |
To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations. |
Initiating Reference: PMBOK® Guide 5th Edition, page 66. |
|
The concept of (the) _________ states that changes related to one requirement—scope, time, or cost—will at least influence one other element |
Triple constraint |
Executing Reference: Sponsoring a Project by Paula K. Martin, |