What are the 2 types of plugs used in UWSH?
|
-Wooden damage control (DC) plugs
-Mechanical Expandible plugs |
|
When plugs are installed on the vertical sides of the hull (above the bilge keel or turn of the bilge), what is perfered over tag lines?
|
Bellybands can help to secure the plug in addition to locating the plug.
|
|
T or F, installation of an internal sealing blank in combination with a closed sea chest valve meets the double-valve protection requirement without a diver installed plug?
|
true
|
|
What must be approved and followed when any diver installed plug serves as the primary or secondary barrier to the sea?
|
FWP, including the patch and plug inspection sheet and the patch and plug installation checksheet that has been approved by the RA and the ships CO or his disignated rep.
|
|
Who must be notified prior to the installation of a plug?
|
The CO or his disignated representative shall be notified of the location of the plug and level of protection provided (single or double protection).
|
|
Who signs off the patch and plug inspection checksheet approving the inspection and where shall it remain on file while the device is installed on the vessel?
|
Dive supervisor signs the inspection checksheet and it remains on file at the installing activity.
|
|
How long shall divers remain on dive station?
|
Until double valve protection is established, repairs are completed or ship's CO or his designated representative permission is granted.
|
|
What must be stamped on the end plate or waterproof tag of a mechanical expandable plug?
|
Size range
|
|
Mechanical plugs must have a seated presure rating of what?
|
At least 1 1/2 times the static pressure head it will seal.
|
|
Due to the potential of galvanic corrosion, mechanical plugs with ________ components are not authorized?
|
Aluminum
|
|
T or F, tapered mech. plugs are authorized for UWSH?
|
False, they tend to dislodge during the tightening process.
|
|
What is required to verify the integrity of the plug upon installation and prior to removal?
|
Communication protocol with the on-site repair personnel.
|
|
How do you verify a positive seal has been made after a plug has been installed?
|
Have SF open a bleed valve installed in the system, or slowly loosen an internal flange.
|
|
What is the maximum a DC plug may protrude from the opening after it has been installed?
|
3 to 4 inches
|
|
What are used on DC plugs as a sealing compound?
|
Binsuke
|
|
How are hull openings identified and located on submarines?
|
SF must identify the location by use of a weighted line hung over the side at the correct frame location. 2 independent DV must verify the correct hul opening is being patched or plugged by returning an onboard tapping signal.
|
|
What is the minimum size wire rope used for bellybands?
|
3/8" wire rope
|
|
How are leak checks conducted on the plug by the DV?
|
By releasing air bubbles around the perimeter of the plug.
|
|
Who must be notified on submarines prior to breaking loose fastners to confirm plug seal?
|
The CO
|
|
What must be verified on all internal installed sealing blanks?
|
A less than 1/2 inch diameter vent valve
|