• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/7

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

7 Cards in this Set

  • Front
  • Back
What are five common reasons for crashing a project?
1. Reducing time to market in order to gain a competitive advantage
2. Unforeseen delays that cause substantial delays midway through the project
3. Incentive contracts that reward reduced project time
4. Imposed deadlines
5. Very high overhead costs
What are the advantages and disadvantages of reducing project scope to accelerate a project? What can be done to reduce the disadvantages?
Advantages to reducing project scope to accelerate a project are that time and cost may be reduced. Disadvantages include the fact that functionality is lost and the value of the project reduced. These disadvantages can be minimized by an intense re-examination of requirements with stakeholders to determine which features are essential. This “may actually improve the value of the project by getting it done more quickly and for a lower cost” (p. 288).
Why is scheduling overtime a popular choice for getting projects back on schedule? What are the potential problems for relying on this option?
Scheduling overtime is a popular choice for accelerating project completion because it avoids the additional costs of coordination and communication encountered when new people are added to a project. Additionally, there may be fewer distractions when working outside of normal business hours and, if the people working overtime are salaried workers, there may not be any real additional cost for the extra work. 

Potential problems with relying on overtime include the increased costs when using hourly workers. Overtime for salaried workers may result in reduced productivity, lower employee satisfaction, burnout or turnover.
Identify four indirect costs you might find on a moderately complex project. Why are these costs classified as indirect?
Indirect costs that might be found on a moderately complex project include supervision, administration, consultants, and interest. These costs are classified as indirect because they cannot be associated with any particular work package or activity.
How can a cost-duration graph be used by the project manager? Explain.
Cost-duration graphs allow the project manager to identify “the costs of reducing project time so that comparisons can be made with the benefits of getting the project completed sooner” (p. 288). These graphs require gathering direct and indirect costs for specific project duration which can help highlight and searching critical activities to find the lowest direct-cost activities that will shorten project duration.
Reducing the project duration increases the risk of being late. Explain.
Reducing the project duration increases the risk of being late because reducing the slack of noncritical activities increasing the likelihood of creating new critical paths. More critical paths increases the risk of the project being late.
It is possible to shorten the critical path and save money. Explain how.
Shortening the critical path can save money in instances where indirect costs are a significant percentage of total project costs. A shorter project means these costs are incurred for less time.