• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/10

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

10 Cards in this Set

  • Front
  • Back
1. Which of the following is not part of the three-sphere model for systems management?
a. business
b. information
c. technology
d. organization
b: information
2. Which of the four frames of organizations addresses how meetings are run, employee dress codes, and expected work hours?
a. structural
b. human resources
c. political
d. symbolic
d: symbolic
3. Personnel in a ________ organisational structure often report to two or more bosses.
a. functional
b. project
c. matrix
d. hybrid
c: matrix
Project work is most successful in an organisational culture where all of the following characteristics are important except ________.
a. member identity
b. group emphasis
c. risk tolerance
d. control
d: control
A _______ is a product or service, such as a technical report, a training, or hardware, produced or provided as part of a project.
a. deliverable
b. product
c. work package
d. tangible goal
a: deliverable
6. Which of the following statements is false?
a. An analysis project life cycle is a collection of project phases.
b. A product life cycle is the same as a project life cycle.
c. The waterfall approach is an example of a predictive life cycle model.
d. Agile is an example of an adaptive life cycle model.
b: a product life cycle is the same as a project life cycle
Which of the following terms describes a framework of the phases involved in developing information systems?
a. systems development life cycle
b. rapid application development
c. predictive life cycle
d. extreme programming
a: systems developing life cycle
The nature of IT projects is different from projects in many other industries because they are very _______.
a. expensive
b. technical
c. diverse
d. challenging
c: diverse
What term describes an organization’s acquisition of goods and services from an outside source in another country?
a. globalization
b. offshoring
c. exporting
d. global sourcing
b: offshoring
________ is the leading agile development method.
a. Extreme programming
b. Sprint
c. Six sigma
d. Scrum
d: scrum