What are two ways to impound funds?
|
DEFERALS
Temporary Must report to Congress RECISSIONS Must report to Congress If no action in 45 days; must be made available |
|
What does a direct MIPR need before obligation?
|
A signed contract.
|
|
When can an obligation be recorded?
|
When there is documentary evidence of the transaction.
|
|
What are the Appropriation life cycles?
|
MILPERS 1
O&M 1 RDT&E 2 Procurement 3 MILCON 5 SCN 5 |
|
What is the Necessary Expense Doctrine?
|
The Purpose part of PTA
|
|
What are the 3 tests of Purpose?
|
Logical relationship to the appropriation
Not prohibited by law Not funded elsewhere |
|
What is the systematic approach to choosing the best method of allocating scarce resources to achieve a given objective?
|
Economic Analysis
|
|
What are the steps necessary to conduct an effective Economic Analysis?
|
Identify constraints
Determine alternatives Identify cost/benefits of each alternative Compare alternatives Perform a sensitivity analysis Report results |
|
What are some limits of EA?
|
GIGO
Cannot make final decisions No cookbook precision Cannot provide relevant solutions to irrelevant problems Cannot predict political or non-economic impacts Not a substitute for sound judgement |
|
What are the 3 linking factors critical to the sucess of any EVMS?
|
Cost
Schedule Performance |
|
What cost structure does MIL-HDBK-881 represent?
|
Defines the general WBS elements by commodity
|
|
What happens at Milestone B?
|
Where program initiation occurs
The MILDEP or Agency is required to have funds in the FYDP |
|
What concept is based on the axiom that the best time to reduce costs is early in the process?
|
CAIV
|
|
Advance procurement is an exception to what principle?
|
Full Funding
|
|
What is the title of the final document of the Planning Phase?
|
JPG
|
|
Who serves as the chair of the National Security Council?
|
POTUS
|
|
Under the Economy Act agreement, what must be done with funds that are unused when the ordering appropriation expires?
|
Returned to the sender
|
|
What document provides guidance to the components regarding the best mix of forces and resources to achieve objectives?
|
Joint Programming Guidance (JPG)
|
|
When is the QDR due?
|
February of the second year of a presidential administration.
|
|
What is the intent of the Integrated Priority List (IPL)?
|
Provide visibility to the key priorities of the Combatant Commanders
|
|
What is submitted in odd years ILO a POM?
|
A Change Proposal
- Must net to 0 - Only require action in off year |
|
What is the SLRG?
|
The Senior Leaders Review Group
The DoD's Board of Directors |
|
What does the Budget do?
|
It translates the Program into an Appropriations format.
|
|
When is the BES submitted?
|
September of even years
|
|
The USD(AT&L) serves as the chair of what board?
|
DAB
|
|
What comprises the BES?
|
The POM w/o the outyears
1 prior 1 current 2 budget |
|
In what years are CPs submitted?
|
Odd years
|
|
When is the POTUS required to transmit the budget to Congress?
|
1st Monday in February
|
|
When is the 1st concurrent resolution due?
|
15 April
|
|
WHAT does the 1st concurrent resolution do?
|
Fixes budget authority and sets outlay targets
Establishes targets for public debt Develps allocation of budget to each committee (Does not go to POTUS) |
|
What is the difference between Budget Cost of Work Performed and Actual Cost of Work Performed?
|
Cost Variance
|
|
What does a direct MIPR need before obligation?
|
A signed contract
|
|
What does the Joint Strategic Planning examine?
|
The global security situation
|
|
What does the Chairman's Program Assessment (CPA) do?
|
Compares the POM/CP with the Issue Books.
|
|
The Director PA&E analyzes the POM/CP and creates what?
|
Issue Books
|
|
Who develops the National Defense Strategy?
|
SECDEF
|
|
Who develops the National Military Strategy?
|
Chair of the Joint Chiefs
|
|
Who develops the Strategy for Homeland Defense and Civil Support?
|
SECDEF
|
|
What is the final output of the PPBE?
|
Submission of the budget to the POTUS for approval and to Congress for authorisation & appropriation.
|
|
What does correlation measure?
|
The degree of relationship between variables.
|
|
Criteria for inclusion into a DWCF?
|
1. ID of outputs
2. Establish a cost accounting system 3. ID of customers 4. Evaluation of buyer's-seller's advantages/disadvantages. |
|
When is the FYDP updated?
|
Twice in even years
- POM/BES - PresBud Once in odd years - PresBud |
|
What financial control document is issued by the Treasury Department following signature of the Appropriations Act?
|
A warrant.
|
|
Key role of the Chairman Joint Chiefs?
|
Military advisor to POTUS
|
|
What is the FYDP?
|
An automated database that summarizes all forces,resources, and equipment.
|
|
Who is responsible for central control and management of the FYDP?
|
Director, Program Analysis and Evaluation (DPA&E)
|
|
What is the duration of MILCON?
|
5 years unexpired; 10 total
|
|
What is the duration of RDT&E?
|
2 years unexpired; 7 total
|
|
What is the duration of SCN?
|
5 years unexpired; 10 total
|
|
What is the duration of PROC?
|
3 years unexpired; 8 total
|
|
Purpose of the PPBE process
|
allocate resources within the Department of Defense
|
|
Key role of the SECDEF?
|
Develops National Defense Strategy and Strategy for HD and CS.
|
|
What is the QDR?
|
Quadrennial Defense Review.
Drafted every 4 years following presidential election. Draw from NDS, NMS,HD and CS. |
|
Key roles of the Chairman, Joint Chiefs?
|
Military advisor to POTUS, NSC, and SECDEF
|
|
Budget estimates are reviewed by who?
|
USD (C) and OMB
|
|
Final document of the planning phase?
|
JPG
|
|
What preceeds PDM in programming phase?
|
POM submits
|
|
In what years is the POM prepared?
|
Even years
|
|
Change Proposals (CPs) are performed in what years?
|
Odd years
|
|
What is comprised of one page outlines of proposed major issues?
|
Issue books
|
|
Checks balances and capabilities of force and support levels recommended by service POMs?
|
Chairmen's Program Assessment
|
|
Helps SECDEF make program decisions reflected in the POM?
|
Chairmen's Program Assessment
|
|
Issuance of this document completes the programming phase?
|
Program Decision Memoranda
|
|
Provides detailed synopsis for the preparation of biennial budget estimates?
|
DoD FMR 7000.14R
|
|
Docs submitted in even number years?
|
BES
|
|
Provides detailed synopsis for the preparation of biennial budget estimates?
|
DoD FMR 7000.14R
|
|
Docs submitted in odd number years?
|
CPs
|
|
Who is responsible for PBD?
|
USD(C)
|
|
What is the FYDP?
|
An automated database that summarizes all forces, resources and equipment.
|
|
What is the purpose of PBDs?
|
Reflect SECDEF decisions regarding program and funding to be included in annual defense budget.
|
|
What's in the BES?
|
PY, CY, BY, BY
|
|
When is the BES modified?
|
Submitted to OSD in September of each even numbered year.
|
|
Who is responsible for central control and management of the FYDP?
|
Director, Program Analysis and Evaluation (DPA&E)
|
|
Who coordinates the annual program review?
|
DPA&E
|
|
What are the phases of the Federal Budget Process?
|
Budget Formulation - Congressional Action - Budget Execution - Review & Audit
|
|
When is the PRESBUD due?
|
Due to Congress NLT 1st Monday in February.
|
|
What is normally transmitted to Congress as request to provide funds in addition to amounts already appropriated?
|
Supplemental
|
|
What is the due date to House and Senate Budget Committees for all Congressional committees on their respective views and estimates?
|
15-Mar
|
|
What is a continuing resolution?
|
Temporary appropriation act that dissolves when a regular appropriation is enacted
|
|
Who must request apportionment?
|
OSD
|
|
What is a deferral?
|
postponement of funds
|
|
What is a rescission?
|
The cancellation of funds
|
|
Within how many days must an agency request apportionment?
|
Within 10 days
|
|
The most common type of obligating document is?
|
contract
|
|
what is the most universal form for requesting work or services from another government entity?
|
MIPR
|
|
What is a rescission?
|
The cancellation of funds
|
|
What is the duration of MILCON?
|
5 years unexpired, 10 total
|
|
The most common type of obligating document is?
|
Contract
|
|
What is the duration of RDT&E?
|
2 years unexpired, 7 total
|
|
What is the duration of SCN?
|
5 years unexpired, 10 total
|
|
What is the duration of PROC?
|
3 years unexpired, 8 total
|
|
When did WCF get established?
|
National Security Act of 1947
|
|
What are funds appropriated but not yet apportioned by OMB?
|
Unapportined appropriations
|
|
What are funds apportioned by OMB but not yet alloted by DoD?
|
Unalloted apportionments
|
|
What is a working capital fund?
|
A revolving fund designed to breakeven
|
|
What is a systematic approach to the problem of choosing the best method of allocating scarce resources to acheive a given objective?
|
Economic Analysis
|
|
When is economic analysis required?
|
>$1M
|
|
When is a cost estimate required?
|
<$1M
|
|
What are the 3 measures of central tendency?
|
Mean, Median, Mode
|
|
What is the formula for discounting?
|
PVF = 1/(1+d)^n
|
|
What is a systematic approach to choosing best method of allocating scarce resources to achieve a given objective?
|
Economic Analysis
|
|
cost structure MIL-HDBK-881
|
Work breakdown structure
|
|
What cost estimating approach is based on direct comparison with historical info?
|
Analogy
|
|
What is the cost estimating approach known as a statistical method or top down approach?
|
Parametric
|
|
What indicates that the best time to reduce cost is early in the process?
|
Cost as An Independent Variable (CAIV)
|
|
This cost estimating approach requires extensive knowledge of the product or process.
|
Engineering or "Bottom Up"
|
|
Advance procurement is an exception to what technique?
|
Full funding
|
|
What is the difference between budget cost of work performed and actual cost of work performed?
|
A cost variance
|
|
What is a radical redesign of key business processes that involves examination of the fundamental process itself?
|
Business process innovation or reengineering
|
|
How many players should be on a business process reengineering team?
|
Less than 10
|
|
After the Appropriation is signed into law, the DoD requests what from OMB?
|
Apportionment.
|
|
What is the purpose of the Programming Phase?
|
To translate planning decisions, programming guidance, and Congressional guidance into a detailed allocation of resource requirements.
|
|
What are the elements of the POM?
|
A systematic analysis of mission objectives to be achieved
Alternative methods of accomplishing objectives Allocation of resources (Even years only) |
|
On 15 Nov each agency head must submit what?
|
Performance Report
|
|
How often must 5-year strategic plans be updated for nonDoD? For DoD?
|
Non = 3 years
DoD - 4 years (QDR) |
|
What are some misc. sources of funds for the DoD?
|
Agricultural and grazing leases
Recycling Sale and outlease Fish and wildlife conservation program Energy savings |