Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
13 Cards in this Set
- Front
- Back
- 3rd side (hint)
Budgeted At Completion (BAC) |
How much was originally planned for this project to cost. |
No one formula exists. Is derived by looking at the total budgeted cost for the project.
|
|
Planned Value (aka Budgeted Cost of Work Scheduled) (PV or BCWS)
|
How much work should have been completed at a point in time based on the plan. Derived by measuring planned work completed at a point in time. |
Planned % Complete x BAC
|
|
Earned Value (aka Budgeted Cost of Work Performed) (EV or BCWP)
|
How much work was actually completed during a given period of time. Derived by measuring actual work completed at a point in the schedule.
EV = Actual % Complete x BAC |
EV = Actual % Complete x BAC
|
|
Actual Cost (aka Actual Cost of Work Performed) (AC or ACWP)
|
The money spent during a given period of time.
Sum of the costs for the given period of time. |
Sum of the costs for the given period of time.
|
|
Cost Variance (CV)
|
The difference between what we expected to spend and what was actually spent.
CV = EV-AC |
CV = EV-AC
|
|
Schedule Variance (SV)
|
The difference between where we planned to be in the schedule and where we are in the schedule
SV = EV-PV |
SV = EV-PV
|
|
Cost Performance Index (CPI)
|
The rate at which the project performance is meeting cost expectations during a given period of time.
CPI = EV ÷ AC |
CPI = EV ÷ AC
|
|
Cumulative CPI (CPI^c)
|
The rate at which the projects performance is meeting cost expectations from the beginning up to a point in time. CPI^c is also used to forecast the projects costs at completion.
CPI^c = EV^c ÷ AC^c |
CPI^c = EV^c ÷ AC^c
|
|
Schedule Performance Index (SPI)
|
The rate at which the project performance is meeting schedule expectations up to a point in time.
SPI = EV ÷ PV |
SPI = EV ÷ PV
|
|
Estimate at Completion (EAC)
|
Projecting the total cost at completion based on project performance up to a point in time.
EAC = BAC ÷ CPI^c |
EAC = BAC ÷ CPI^c
|
|
Estimate to Completion (ETC)
|
Projecting how much more will be spent on the project based on past performance.
ETC = EAC - AC |
ETC = EAC - AC
|
|
Variance at Completion (VAC)
|
The difference between what was budgeted and what will actually be spent.
VAC = BAC - EAC |
VAC = BAC - EAC
|
|
To-Complete Performance Index (TCPIc)
|
Performance that must be achieved in order to meet financial or schedule goals.
TCPIc = (BAC - EV) ÷ Remaining Funds |
TCPIc = (BAC - EV) ÷ Remaining Funds
|