• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/61

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

61 Cards in this Set

  • Front
  • Back

Which parts of the crane is the (lifting) radius measured from?

Centre of slew ring to the centre of the hook.

a)What is the purpose of a method statement?


b)What is required of the operator?

a) To give instruction on a specific task and how to do it safely.


b) Crane operators MUST ALWAYS work towards method statement

What is the difference between a CONTRACT LIFT and a STANDARD CRANE HIRE?

CONTRACT LIFT: Crane company plan and supervise the lift




STANDARD CRANE HIRE: Work to hirers company lift plan.

What is jib deflection and when does it occur?

Bend/sag in the jib happens when lifting heavy loads.

a) What is meant by the lifting capacity of the crane?


b) Who determines it?

a) The maximum a crane can lift depending on the configuration.




b) The manufacturer determines this

What is the purpose of the cranes counter-weight?

Reduces over turning effect.

A tower crane has been delivered to site, assembled and configured for lifting. What must be carried out before lifting? and by whom?

Must be inspected by an authorised competent person.

If a load of 20 tonnes is lifted on four falls of rope what is the tension in each fall?

5 Tonnes ( 20/4)

The safe working load or working load limit (SWL/WLL) of a multi leg chain sling only applies in what TWO configurations?

1, Each leg is equally loaded


2, Within 90° of eachother (45° from vertical)

If fitted what is the purpose of having flags situated on the jib?

To show the radius of the crane and safe working load at that position of the jib.

Only 2 legs of an 8 tonne 4 legged chain sling are used, what is the maximum load that can be lifted?

4 tonnes. (8/2)

Why should luffing jibs be placed in the correct out of service position at the end of the day?

To allow the crane to weather vane.

If setting up to lift loads near a pedestrian aream what main factor needs to be taken into account?

The segregation of pedestrians from overhead loads using barriers, exclusion zones and other resources.

a) at the end of the shift what FOUR security measures should be applied?


b)Why?

a)


1, Isolate crane controls


2, Lock cab door


3, Turn off Power


4, Secure access to crane at ground level.


b) you do not want any unplanned movement of the crane, and you do not want any unauthorised access to the crane outside of working hours.

What does the Health and Safety at work act require employers to do with regards to plant?

To provide plant that is safe to operate and maintain (so it poses no risk to health)

What determines the minimum distances that any part of plant and machinery has to be kept from overhead electricity lines?


Explain why a distance must be kept.

The minimum distance is determined by the voltage of the over head electricity lines.


Electricity can ARC and jump across gaps.

If the words STOP NOW are given to the crane operator by radio during the lift, what action must the operator take.

Stop control of crane in a controlled and safe manner.

Wind speeds can be variable throughout the working day, what actions must be taken to ensure safe working conditions are maintained?

Lift loads carefully and check wind speeds regularly with the Anemometer.

If radios are to be used during the lifting operations what FIVE actions and checks must be made bu the crane operator before use?!

1, Check batteries (carry spares)


2, Check radios are working


3, Set to the correct channel


4, Make sure it is UHF/VHF licensed


5, Check signal strength



a)How does the number of lines or falls of rope affect the lifting capacity of the crane?


b)How is hoist speed affected when the number of lines is reduced?

a) It affects the lifting capacity.


b) The hoise speed increases when lines are reduced.

List SIX typical subjects that should be covered in a site induction.

1, Fire safety


2, Accident/near miss reporting


3, Correct PPE


4, Waste disposal


5, Dust control


6, Traffic routes




(toilets/access and egress/emergency procedures etc)

What is the main purpose of the rated capacity indicator.

To give warning of when the crane approaches or exceeds maximum rated lift.

What is meant by a floor climbing tower crane?

Cranes situated in the lift shaft, they rise as the building goes up.

What re the possible outcomes of facing prosecution for not complying with legislation and regulations?

Fine/Imprisonment.

Name THREE ways that a hired in crane driver can contribute in ensuring repeat business?

1, Work Safely.


2, Cooperate with others.


3, Be punctual.



Name THREE ways in which a crane operator can reduce their impact on the environment.

1, Efficient use of the crane.


2, Correct waste disposal.


3, Prior planning of lifts.




( have a well maintained crane)

If a load is slewed rather quickly what two inital effects does it have on the load whilst slewing?



Load can trail the jib causing load to swing outwards increasing the radius.

What is the definition of a hazard?

A danger or a risk.

Name THREE ways in which wind speed can affect the lifting operations.

1, Increase/decrease slewing speed.


2, Creates load swing (can put load outside of radius)


3, Can stop lifting operations.

State the functions of the following roles: a) Appointed person


b) Crane Supervisor


c) Crane operator


d) Slinger/Signaller

a)


-Overall planning and reviewing of lift plans


-Production of risk assesments.


-Leading team and making appointments.


-Ensuring examinations and inspections are carried out.


b)


-Supervising to ensure method statements are being followed and that work is being carried out safely and efficiently.


c) Setting up and operating crane to given instruction.


d) Attaching and detaching loads and signalling and communicating with crane operator.





a) In what environments are luffing units commonly used?


b) why are they used?

a) Luffing units are used in built up areas.


b) It can operate in tight areas and reduces the problem of over sailing over adjacent buildings.

Where should the operators manual be kept and why?

In the cranes cab for easy reference.


Other people may need to see it for example Maintenance staff, erection staff and supervisors.

Why is it important to follow manufacturers procedures precisely when assisting in setting/erecting up a crane?

To avoid accident, incidents or damage to the crane.

At the end of the shift:


a) How should cab cleanliness be maintained?


b) Explain why.

a) Take your rubbish with you at the end of the day.


b) For the comfor and hygiene of yourself and other crane drivers.

If a load is being slewed at a speed too high for it's size, What TWO factors must the operator and signaller take into account?

1, Time and distance to stop.


2, Excessive swing, snatching and shock loading.

When slewing with a load, where should the operator be looking?

Operator should be looking ahead of the load.

What prevents the hook blokc from contacting the jib pulley?

The cut out/limit switch.

What THREE main duties of the health and safety at work act must employees follow?

1, Take care of ourselves and others.


2, Cooperate with employer.


3, do no recklessly or deliberately interfere with health and safety issues.

Name TWO ways that wet weather can affect lifting operations.

1, Loads can become heavier (porous materials like sand)


2, Reduced visibility.

What is meant by a cast in base?

Crane is cast into a large concrete pad or in building foundations.

The operator has to use a new model of crane that he is not familiar with. What do regulations (ie LOLER 98) require the operator to check?

Make sure that you have correct training, information and instruction.

On a busy site, how would a slinger be identified?

By their PPE.

What do the work at heights regulations require of tower crane operations.

Control measures in place to reduce the risk of falling.

Why are hard hats needed for climbing tower cranes?

Falling objects and bangs to the head.

a) Where must the load radius diagram be located?


b) What information must it contain?

a) On the base of the crane.


b) Information on safe working load at different radius and which configuration of rope/falls.

What problems can be created when operating a crane in high speed drive?

Excessive swing, snatching and shock loading.

What effect can a swinging load have on a crane?

It can create unstability of the crane and can increase the loads radius.

What are the THREE actions a crane operator must undertake during pre use inspections?

1, Check Manufacturers recommendations.




2, Check base of crane for the load radius diagram to check for information on SWL at different radius and different configurations of rope/falls.




3, Check operations manual.



Why are crane operators considered safety critical workers?

Because their actions have serious health and safety consequences to themselves and others.

The number of falls has been changed on the hook, how has this action affected the RCI?

It has changed the lifting capacity of the cran, The RCI needs to be adjusted.

Apart from the operator who else needs to use the machines operator manual?

1, Maintenance staff


2, Erection staff


3, Supervisors.

Name FIVE requirements that must be followed if accessing the end of the jib for maintenance purposes?

1, Authorised.


2, Harness trained.


3, Correct PPE


4, Good weather


5, Rescue plan in place.

Two cranes are working in the same vicinity that encroaches on the operating radius of each.


What actions would the lift plan/method statement normally specify?

Method statement/lift plan would need to specify limits on slewing.


(requires good communication between signaller and operator)

If the hook block inadvertently lands, what course of action should be taken?

1, Hook block checked for damage


2, check rope alignment


3, check crane drum for rope crossover


4, find out why it happened.

Why are some tower cranes rail mounted?

So that they can cover a larger working area.

what is the purpose of a risk assesment?

To Identify hazards and place control measures on them.

What makes up total gross weight of a load?

1, Load itself.


2, Hook block.


3, Lifting accessories.



Why must tools not be kept on deck?

Prevents trips, slips and falls.

During the lifting operation, part of the task cannot be carried out as detailed in the lift plan.


a) What initially must happen to lifting operations?


b)by whom?

a) Work must STOP


b) Appointed person.

Name FOUR types of disciplinary action that employers and judicial bodies can apply to operators who do not comply to rules and legislation?

1, Verbal warning


2, Written warning.


3, Dismissal.


4, Prosecution.

How can a qualification or card benefit an operator?

Proof of training and competency to employer.