Productivity components
|
person, tools, task, method, organization, environment
|
|
Pareto analysis |
where to focus attention and efforts, identify what causes the most quality problems |
|
Fish diagram |
cause and effect diagrams, used to determine the root causes of a problem |
|
Gantt chart |
used to put operations in sequence and manage the project time |
|
Pert chart |
a scheduling tool that uses the longest path or the critical path to determine the minimum time to complete a project |
|
Work element sharing |
operators with idle time share work of another station |
|
Operation analysis |
a continuous process of review of current operations, and part of planning process for new operations |
|
Variance |
(1/6(longest time-shortest time))^2 |
|
Expected values |
1/3(2*middle time+.5(shortest+longest)) |
|
Standard deviation |
Add variances on critical path and square root |
|
Operations approaches |
purpose of operation, part design, tolerance and specs, materials manufacturing, set up and tools, materials handling, plant layout, work design |