C.E.1.1 INTRODUCTION:
C.E.1.1.1 DURATION: 15thMarch, 2015 to1stJune, 2016
C.E.1.1.2 LOCATION: Trelleborg Marine System India Pvt. Ltd.,17th Floor, Westgate B- Block, YMCA Club S.G. Highway, Makarba, Ahmedabad, India.
C.E.1.1.3 COMPANY: Trelleborg Marine System India Private Limited.
C.E.1.1.4 POSITION:JR. DESIGN ENGINEER
C.E.1.2 BACKGROUND:
C.E.1.2.1 PROFILEOFTHEEMPLOYER:
Trelleborg Marine Systems is world’s largest Marine Fender manufacturer, which have thousands of fender systems installed around the world including almost every principle port in the world. As a part of Swedish Multinational, “Trelleborg AB” has USD 2.5 Billion annual sales and 16,500 employees globally. Unlike many other companies in the market …show more content…
Trelleborg AB is a global engineering group focused on polymer technology, with headquarters in Trelleborg, Sweden. It has operations in 50 countries and describes its mission as the development of “engineered polymer solutions that seal, damp & protect critical applications in demanding …show more content…
• Maintaining high-quality model and drawing output.
• Maintaining accurate content in drawings and documentations.
• Ensure Information on drawings and documents are correct and complete.
• The successful and timely delivery of all drafting and modeling work allocated to me.
• Ensure models and drawings created/issued for any product are good for manufacturing.
• Working with defined company processes and standards.
C.E.1.3 PERSONAL ENGINEERING ACTIONS:
C.E.1.3.1 Kick start of the project, KARRATHA GAS PLANT SISO SYSTEMS, was started with training of ten days on basics of SISO system which is ultimately a patent system from Trelleborg. With the help of past projects and the help of and seniors, I got clarification of the objective of Project that included the SISO system for Berth 1 and Berth 3 Karratha gas plant situated in western Australia (As shown in below image 1).
C.E.1.3.2After the understanding of the objective, I started an initial study of the scope of the project provided by the client. The scope challenges are listed below for berth 1& Berth 3.
1. Replace Yokohama air block