Risk Analysis: Submarine Cable Network

Improved Essays
Risk Analysis All of the parties involved have been very optimistic for the outcome of this multinational project, since they had been very well prepared to minimize the risks and uncertainties that might come during the completion of this project. Therefore, most people assumed that SCCN as one of the leading greenfield project for submarine cable network in the world that was financed in Australia and New Zealand. Just like any other project ever conducted, this project did not come without any risks involved. Some of the risks identified prior to the execution of the project, they were: Completion Risk, Market Risk, Infrastructure Risk, and Force Majeure Risk. These risk had been excellently mitigated by designing a good financial structure, choosing the best suppliers, good marketing strategies, as well as having well trusted sponsors and other parties that provided a strong back-up for this project. Below are further detailed explanations of each risk. • Completion Risk Completion risk comprises all of the risk factors that are led to the disruption of completing the hardware for this project (submarine cable network) as well as the system for this project. Some of the risk factors are operating technology, operating management, completion and supply. SCCN has successfully mitigated the risk by choosing the most experienced and well-known suppliers to handle the supplies for submarine cable network. In this part particularly, Alcatel and Fujitsu were chosen as the major supplier for the submarine cable network because they are believed to have the ability and financial capacity to deliver the best quality product from their previous involvement in similar projects. Moreover, this project had a contract of fixed in price and fixed in time supply that gave the incentive to the supplier to perform and deliver based on the required standards and the timetable. To minimize the risk further, 5% contingencies are added to the supply contract with another 2.5% as an additional equity support from the sponsors in case the first contingencies had been fully used. • Market Risk Market Risk is explained as an exposed risk due to the output produced by the SCCN, which is the capacity used for the network in this case. This risk also took consideration the existing competitors for this project. At the beginning of the financing process, the sponsors for this project believed that SCCN has so much potential as the most advanced technology that is offered to the market of fibre optic capacity compared to the existing submarine cable such as PacRim East and West, which almost reached their maximum capacity. Backed up with two independent market studies, the sponsors were assured that the future market would be very promising once the project is completed. To mitigate the risk, pre-sales program for the capacity of usage was designed for the assessment of financial viability and the market appetite itself. The pre-sales was offered to the major regional and international carriers with additional incentives bonus program for those who signed up for early commitment. The pre-sales also proposed a flexible basis where the carriers are enabled to choose the segment of capacity based on the scheduled capacity payment rather than up …show more content…
• Infrastructure Risk
In this type of risk, the risk factors that were identified are related to the infrastructure needed to support and complete of the submarine cable network. Factors such as route survey and route selection for the cable network that must be placed in the right area, needing for further research and study in order to get the most efficient route. Therefore this project done the finalization of desktop study and completion of route survey before the financial activity ended in order to mitigate the risk and got the route well planned.
• Force Majeure
…show more content…
In case of SCCN, this kind of risk are mitigated by having an excellent design on the part of the cable itself, as well as supporting programs, facilities and infrastructure. The cable were designed to always be available more than 99.99%, with the downtime period predicted to be approximately 50 minutes every 10 years, which represents substantial improvement on the existing average single-strand trans-Pacific cables that only has availability of 98% with 66 days downtime every 10

Related Documents

  • Decent Essays

    Upon determining what should be in the intranet, what risk is the organization willing to tolerate should be tackled. An assessment of the privacy controls and security controls can be determined by using NIST Special Publication 800-53A: Assessing Security and Privacy Controls in Federal Information Systems and Organizations, Building Effective Assessment Plans as a guide along with NIST Special Publication 800-30, Rev-1, Guide for Conducting Risk Assessments (NIST SP 30-1, 800-53A). To truly understand this publication is prohibitive to fully explain; however, this step is critical and will impact your intranet dramatically. To simplify: you cannot always have the risk metric you desired because by doing so would make your system so slow and unusable you could not accomplish much.…

    • 428 Words
    • 2 Pages
    Decent Essays
  • Great Essays

    AMT2 Service Line Development Task 4 Echo Breen A. Determine the feasibility of one of the proposed service lines in the attached “Service Line Development Case Study” by doing the following: A1. Evaluate the demand for the new service line in the market area defined in the case study. Trinity Community Hospital (TCH) has the opportunity to develop a new orthopedic service line. It is anticipated that there will be a huge increase in need for orthopedic services within the next 5 years; orthopedic cases will increase by 46%, joint and spine procedures will increase by 30% and outpatient joint and spine procedures will increase by 350%.…

    • 1461 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    This case is a very good example of a good project management with high risk management. This case talks about the importance of project management process and risk management. Their approach to project management is bottom up, executive teams don’t tell project teams what to do, it project managers and project teams who provide project plans and analyse the risk and decide whether to do the project or not. Project teams take at least 6 months to bid for a RFP, and when they win the bid they know what they are going to do next. They are having a unique approach towards risk management and compliance process.…

    • 701 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    A lot of things can go unexpectedly and could have a negative impact on the company o Contractor missing deadlines will cause a delays and additional costs o Forecasted sales for products could be inaccurate o Shortage in capital, man power and materials could have a negative impact on DSF • Financial risk – DSF is at high risk with this move. Within three years, the company has to spend over 25 million lbs. in new equipment. o DSF will most likely acquire debt for this initiative which could lead to negative consequences if construction plans delay  The organization image could be damage if they can’t meet supply  The alliance members such as banks and investors could also be negatively impacted • Operational risk - Risks that affects ongoing management process shouldn’t be affected.…

    • 993 Words
    • 4 Pages
    Great Essays
  • Improved Essays

    The statement above, reflects the fact that, the Boeing 787 Dreamliner project team did not proactively assed the risks, of implementing different methods of supply chain, consequently there wasn’t a coherent and strategic risk mitigation plan. Despite, being difficult to identify all the risks in the beginning of the project, Boeing management team, could have done many things in a different…

    • 2435 Words
    • 10 Pages
    Improved Essays
  • Improved Essays

    Identifying and managing risks is a critical responsibility of project managers. Risk is defined as the probability of a specified threat and the subsequent impact that the event produces (Vaidyanathan, 2013). Risks can also bring about either positive or negative outcomes for a project or organization. A project manager must identify potential risks and evaluate each one to determine the severity and likelihood of each event. Only by completing the risk management process, a project manager can determine what approach would work best to avoid, mitigate, and/or transfer the risk.…

    • 730 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    Trans-Shipment Container Management in the Port of Piraeus Theodoros Koromilas ABSTRACT As a mainly trans-shipment container port, the container terminal of the port of Piraeus has as a primary goal to provide equipment and facilities to deliver efficient and professional service. The commercial port of Piraeus consists of three (3) container terminals, of which one (1), Terminal I, is being operated Piraeus Port Authority S.A. (P.P.A) and two (2), Terminal II and III by the Piraeus Container Terminal S.A. (P.C.T.), which is a subsidiary of COSCO Pacific. Head offices are located behind their terminals for each organization.…

    • 1356 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    Risk Management Organisational Context:- The FIFA organisational context refers to the scope of the body, such as • FIFA (Parent organisation) • Enterprise and a sub-organisation • Work unit and Work Role Three Perspectives:- To gain the comprehensive understanding of the organisation context for World Cup Strategic- Focus on the long-term need within the organisation to ensure things. Tactical- Focuses on the event, FIFA World within the organisation to ensure the effectiveness.…

    • 1083 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    Risk management is a critical element of all projects. Boeing can do so by identifying the risk then prioritising the risks based on its risk of occurrence and impact then make a plan to reduce and hopefully avoid such risks. The project will have a higher chance of being successful when the risks are anticipated prior to their occurrence. In May 2015 Boeing found that their engine would automatically shut down due to long use of the engine. This is extremely dangerous to many lives if they don’t have a backup…

    • 862 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Case Study Of Gwadar Port

    • 1812 Words
    • 8 Pages

    CHAPTER-4 THREATS TO GWADAR PORT 4.1 Internal threats. Internal threats to this project have many dimensions and these will be discussed in following sequence:- a. Political dimension b. Internal security dimension c. Issues related to Infrastructure d. Economic Aspects e. Social dimension 4.2 Political Dimension a. Province of Baluchistan has typical demographic and social pattern in which Sardars have been yielding power since long. The local and provincial Sardars are trying their best to politicize this project. b. Baluchistan’s influential Sardars, where the project is located, are once again against the Federal Government.…

    • 1812 Words
    • 8 Pages
    Improved Essays
  • Improved Essays

    After vulnerabilities are identified, we should proceed and identify threats that can harm or affect critical operations and assets. The next step is to develop a Risk Profile which lets us analyze and rank risks according to their impact to the environment. Lastly, risk reduction plan needs to be developed. Here we need to evaluate existing…

    • 980 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    .The cardinal reasons responsible for hazardous activities as per these code of conducts are emission of inflammable or toxic fluids due to leakage problem, lost control over controlled operational processes, sudden fires or explosion on working site due to short circuits and last but not the least is damage to structure of transportation ships and carriages due to collision leads to total failure of ship or carriage. In order to support these rational facts, some incidents can be analyzed from the past that will provide a crystal clear view to the scenario (Godoy et al. 2012). In year 2009, a very strong and reputed company of India ,Indian Oil Company has its plant in south side of Jaipur where during a particular operation of transferring…

    • 1227 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    System Week Reflection

    • 927 Words
    • 4 Pages

    Reflection of Learning 3 Systems Week Systems week was a valuable experience in my engineering degree, and certainly one of the most memorable weeks of university. Usual courses taken as a part of my specialisation are largely theoretical, and may not be sufficient to develop certain necessary for engineers. Systems courses aim to bridge this disparity between industry needs and specialisation courses taught at university. Systems week is definitely a highlight in the system course. In particular, it provides students the opportunity to work in large groups to tackle a project, similar to those engineers may encounter in the industry.…

    • 927 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Poolco Case Study

    • 1677 Words
    • 7 Pages

    In test system-II, primarily a two area multi source power system is considered with three GENCOs and two DISCOs in each area is shown in Fig. 8. The control area 1 and control area 2 comprises of reheat thermal, hydro and gas power system with the inclusion of non-linearities such as boiler dynamics, time delay (TD), governor dead band (GDB) and generation rate constraint (GRC). Boiler dynamics configuration is incorporated in thermal plants to generate steam under pressure. Changes in the steam flow and deviations in pressure are sensed, and the corresponding action is initiated by the turbine control valves and boiler control the steam flow and deviations in pressure are sensed, and the corresponding action is initiated by the turbine control…

    • 1677 Words
    • 7 Pages
    Improved Essays
  • Improved Essays

    1.0 Construction After the submarine cable has been designed inch-perfect, it is the next step where skills of geography are required. The construction of a submarine communications cable is not an easy matter. Furthermore, it is not an inexpensive job too. Skills and knowledge are required by engineers and workers whom are laying down the submarine communications cable. To ensure that the millions of dollars invested on the cable do not go to waste, every single precaution step must be taken to protract its life and in the same time the cable has to be laid in places where repairing even can take place easily if there is any damage has occurred to the cable.…

    • 3621 Words
    • 15 Pages
    Improved Essays

Related Topics